Nevada Irrigation District - Banner Cascade Pipeline Project
Home Page Schedule Public Consultation Contacts Documents FTP Site

Project Schedule

Key dates for the project are listed below. These dates will be regularly updated and further information included as it becomes available

Design Phase starts January 2008
  • Issue of letters requesting Right-of Entry from property owners for survey and investigation purposes
February - April 2008
  • Field Reconnaissance visits by the Design Team
April 17 & 18, 2008
  • Ground Survey
April - June 2008
  • Geotechnical investigation with drilling in the field
June - July 2008
  • Initial 'One-on-One' consultation in the field with property owners by the Design Team, and initial meetings with community associations
June - July 2008
10% Level Design Report and initial pipeline alignment submitted to NID June & July 2008
  • Public Meetings to review the initial pipeline alignment
July 24, 2008
  • Further 'One-on-One' consultation in the field with property owners by the Design Team, and meetings with community associations
June - October 2008
50% Level Design submitted to NID December 2008
  • Public Meeting to review the 50% level pipeline design
January 15, 2009
Appraisal of Parcels for ROW Acquisition March - August 2009
Negotiation for ROW Acquisition May - September 2009
'Substantially Complete' Design submitted to NID April 2009
  • Public Meeting to review the 'Substantially Complete' pipeline design
May 19, 2009
Final Design and Bid Documents submitted to NID October 2009
Contractor Pre-Qualification June - September 2009
Bid Phase (Pre-qualified bidders only) November 2009 - January 2010
Construction Contract(s) awarded by NID January 2010
Construction starts February 2010
Construction finishes December 2011
Banner Cascade Pipeline put into service January 2012